Blue Ribbon - Lincoln Avenue 2007 Street Project
|
Minutes of the Blue Ribbon Core Committee Meeting Held on Monday December 18, 2006 Present were: Steve Lendosky, Pam Kreul, Linda Parrish and Margaret Sprague. Steve Lendosky gave the following report from the Fundraising Committee:
The committee reviewed the bid totals for the project. The low bid was $5,149,735 from A-1 Excavating, Inc. of Bloomer, Wisc. The City/Utility will pay approx. 25-30% of this. Steve Lendosky reported on signage and advertising. Signs will arrive in February and will be installed in April at the four entrances to the City. Bill Wood will provide the posts. Queen B Radio will work with us on radio communications during the project. Nothing new to report from the Beautification Committee, Streets Research Committee or Downtown Business Focus Committee. Distribution of funds raised by the Fundraising Committee was discussed. The four large signs at the City's entrances will be paid for from these funds. However, the smaller signs to be placed along street intersections in the City will be paid for by businesses. Steve Lendosky will communicate this to businesses and through group meetings, including the February 8th and April 5th Chamber meetings. Expenditure of other funds will be authorized through committee communications via email. Employee parking during the construction will also need to be discussed with businesses. The meeting was adjourned at approx. 12:30 p.m. The next meeting will be held January 18th. |