Blue Ribbon -- Lincoln Avenue 2007 Street Project
Construction Update
May 28, 2007
Submitted by Linda Parrish, Promotions Coordinator 608-822-3599, Toll Free 800-822-1131
Trierweiler Construction paving crew has completed pouring intersections and the parking lanes on Fennimore's south city limits to 12th Street. The construction crew will work this week on curb and gutter, sidewalk and driveway entries. A-I Excavating will then begin back filling in preparation for landscaping work scheduled to begin June 4.
The City of Fennimore crews will complete some work this week on Madison and 16th Street this week in preparation for new pavement in that area.
Some questions have been asked in regard to trenches that have been cut out of new pavement between 12th and 14th Streets. Trierweiler Construction has cut these trenches which will be used for color cross walks. Color cross walks will be installed throughout the business district as part of the road construction project.
At this time phase two of the road construction continues to stay on schedule. A-1 Excavating expects phase two of road construction to be completed by June 29 and open to traffic prior to the first week of July.
Mathy Construction is scheduled to begin stage three on Monday, July 9. However, if weather permits stage three may be moved ahead to begin the last week of June. Stage three will consist of grinding off road surface just east of the 12th and Lincoln Avenue intersection to Marsden Park Road. The detour route for stage three for Hwy 18 east bound traffic will be U. S Hwy 61 South to Cty Hwy E and Cty Hwy F and back to US Hwy 18. Local traffic will be able to use side streets to access business and residential areas on Fennimore's east side. Phase three is expected to last about 2½ weeks.
In preparation for stage 5 (expected to begin in October) of road construction new storm sewer has been installed at the junction of Lincoln Avenue and 4th Street. Iverson Construction completed laying temporary mat to widen the intersection.
I have heard many great compliments from city residents who praise crew members from A-1 Excavating for their cooperation and communication with local residents during this stage of the construction project.
It is extremely important traffic stay out of the construction area at all times. The Fennimore Police has been asked to start ticketing drivers who are driving in construction areas. Matt Young, of A-1 Excavating Inc. reminds drivers they will be held liable to replacement costs for any damages done to the road construction area or construction equipment. Please help us spread the word when road construction signs indicate local traffic only they refer to the individuals who actually live on Lincoln Avenue or other streets directly affected by road construction. Your cooperation will help to keep the road project on schedule.
The next public meeting called by WisDOT project engineer Jeremy Krachey will be held Monday June 18 (note date change). The meeting will be held at the Fennimore Memorial building 860 Lincoln Avenue starting at 5 p.m. This meeting is open to the public and especially those residents and businesses affected by the current portion of road construction. Krachey is available at the WisDOT field office located at 1030 Lincoln Avenue or call 608-822-3992.
Previous Construction Updates
- August 10, 2007
- July 30, 2007
- July 19, 2007
- July 16, 2007
- July 2, 2007
- June 25, 2007
- June 18, 2007
- June 15, 2007
- June 8, 2007
- June 4, 2007
- May 28, 2007
- May 21, 2007
- May 14, 2007
- May 7, 2007
- April 30, 2007
- April 23, 2007
- April 16, 2007
- April 9, 2007
- March 26, 2007
- March 19, 2007
- March 13, 2007
- January 10, 2007


